Thursday, December 26, 2013

We have a roof - sort of...

Well, timelines were pushed out again. We didn't make it to lockup by Christmas. 

We have had the plumbing roughed in, foil insulation wrap and roof sarking done, roof tiles laid (ridge capping is still to be fixed into place) and hubby ran some conduit for data and alarm cables. 

Ensuite wall mixer plumbing

Kitchen sink plumbing 


Powder room basin wall mixer plumbing 


Bathroom plumbing. Bath spout under the window, bath wall mixer on the other wall and you can just see the basin wall mixer plumbing to the right

Laundry plumbing

Roof sarking

Roof half tiled

Roof tiled. Ridge capping is still to be fixed into place. 

Hubby putting some extra timber in the frame for the family room TV bracket

Conduit and draw wire for theatre room projector. 

Looks like the tradies have made themselves a swing on our deck downstairs :-/ 


We have been told that the bickies will be back after the first week in January and the electrician will commence his rough in 13th January 2014. Aiming for lockup by the end if January. Fingers crossed! 