Gas connection delays

We received an email from Origin Energy today who confirmed that they attended our site last week but couldn't dig the trench for the gas service line due to the scaffold being in the way and the site not being clean. We have forwarded this email to the builder for their attention. The email also instructed that the builder has to rebook the job once the site has been cleared and scaffold removed. It's usually a 28 day turnaround time for gas connections so that's not looking good for our 5th May handover date :(

The brick window sill has been redone on the master bedroom window which is great. The broken window wasn't covered up again so I hope it doesn't rain. 


Most of the doors were rehung after painting and there are quite a few that do not close properly. I hope this is a simple adjustment.