This is the progress for the last couple of weeks.
Some windows have been installed
Opening for the double stacker door. That tree HAS to go!
Staircase to the right
Man cave bathroom
The bricking was then commenced. I laughed when I saw the foil insulation. We are not using that builder so I have no idea where that came from. Oh well...
Store room walls then started to be bricked up. These will be cavity filled double brick walls - no timber frames.
Some bars were then put in.
Bolts into the slab for the upright steel posts that have to help support the big "I" beam that will go above the stacker door.
One of the upright posts. Clearly not upright at his point in time.
We had terrible weather this week. The only dry days were the weekend ***rolling eyes*** Storms are predicted for tomorrow ***sigh***
I'm hoping the weather can hold out so they can get a decent amount of work done this week.
No comments: