Some facts:
It has been TWO WEEKS since any trades were on site - excluding the trades we organised (balustrades and driveway) and excluding the site supervisor who was cleaning up on Monday.
We are more than THREE MONTHS past contract. That is three months over on a 12 month build contract. It has been more than 15 months since we commenced building.
Each month that ticks over is now costing us THOUSANDS per month in additional mortgages and furniture storage fees.
There are still things to be rectified that are outstanding. We flagged many of these issues with the builder MONTHS ago.
We were obviously naive in thinking that there would be a hive of activity trying to get us to completion as they are so far over contract. The way things are looking we are lucky if we get to move in by August.
We are both OVER IT.